Our Causes: Transport

Building a Connected and Sustainable Mfangano Island

Ferry Services

Ferry Construction

Budget Allocation: Ksh 600 Million

  • Ksh 300 Million from FY 2022/2023 Financial Budget (already banked by KPA).
  • Additional Ksh 300 Million in FY 2023/2024 Budget.
  • Ferry construction is ongoing at Kisumu Shipyard, with an estimated delivery in September 2025.

Sena Pier Upgrade and Rehabilitation

Sena Pier Upgrade

Cost: Ksh 1.2 Billion

  • Approved for upgrade and rehabilitation.
  • Public participation by KPA already completed.
  • Work to commence soon as land is not an issue.
  • Includes Piers at Kendu Bay, Homa Bay, and Mbita.

Access Roads

Access Roads

Budget Allocation: Ksh 10 Million (County FY 2024/2025)

  • Funds allocated for Soklo, Ugina, and Sena-Kibanga Access Roads.
  • Follow-up needed with the National Government to upgrade the Mfangano Ring Road from Murram to Bitumen Standard (Tarmac).
  • Promise made by President William Ruto during the commissioning of the road on 7/8/2023.

Mfangano Ring Road

Mfangano Ring Road

Cost: Ksh 299,871,526.50

  • 53 KM of road to be upgraded to Bitumen Standard (Tarmac).
  • Follow-up with the National Government to fulfill the promise made by President William Ruto during the commissioning of the road on 7/8/2023.

Sena Airstrip

Sena Airstrip
  • Need to consider building a new airstrip or rehabilitating and upgrading the existing one at Sena.
  • County currently engaging with the National Government for the expansion and upgrading of the Kabunde Airstrip.
  • Sena Airstrip to be addressed afterward.

Network & Internet Connectivity

Network Connectivity
  • MDF to engage Safaricom on frequent network failures and the need for improved internet connectivity on Mfangano Island.
  • Tourism attraction necessitates reliable network connectivity.
  • Recent network challenges experienced from 28/12/2023 to 2/1/2024.

Road Last Mile Connectivity

Road Last Mile Connectivity

Budget Allocation: Ksh 88,000,000.00

  • This project is at 80% design stage and 70% complete.
  • Ensures connectivity in all 11 Sub Counties.